Work process for rock splitter

Apr 03, 2020 Leave a message


rock splitter-work process

Application:

1. Drilling

Create a free face by drilling slots in the centre,bottom or periphery.Then drill split holes for

the splitter between the slots.The drawing below exemplify some recommended drilling

patterns.

2. Splitting

Use a splitter mounted on a customized carrier equipped with telescopic boom and

rotate.Start splitting the holes closest to the free face and aim at working from the bottom

up to allow support from gravity.

3. Secondary breaking

Break out the cracked rock into smaller pieces using a hydraulic breaker mounted on a

conventional excavator.Work along the cracks caused by the Zhongtuo splitter.